19.05.2021Projects

House "Beijing" in the multifunctional complex "Minsk World"

We continue to talk about the progress in the construction of the house "Beijing" in the "Minsk World" multifunctional complex, where Stroitegia acts as the general contractor.

The fast-growing quarter is gradually beginning to take shape in its final form. "Beijing" will be the fourth building in the block, which will soon be commissioned.

Let us remind that the object is a five-section corner building designed for 708 open-plan apartments and 25 floors high. The house is located at the intersection of Aerodromnaya street and the new Belgradskaya street, and a new metro station will soon appear next to the block.

On the territory of the former airport, our team has already done and continues to do a tremendous job in the “Champions” quarter.
The construction of the house "Beijing" (18.1 h / p) is proceeding according to the schedule, and over the last month we have started the construction of monolithic porches, insulation and painting of the facade in sections 1 and 2, as well as the construction of window blocks.

In the photo you can see that the crane is being dismantled, since all the roofing work has been completed.

Inside, work continues on tiling, plastering and painting common areas.

At the moment, the installation of external water supply, sewerage and heating networks is underway, after which the Stroitegia team will begin to improve the territory.